Works have progressed greatly since the last update. The building is really taking shape and internally the finished product is clear to see.
All internal walls are built and the layout of the school is in place Plastering is now complete for 50% of the building allowing finishing trades to follow behind including the installation of door frames, first coats of paint and second fixing of electrical items - sockets and light switches.
All external windows and doors have now been installed and the brickwork is nearing completion. This will allow scaffolding to come down over the next coming weeks which will put the finished building façade on display for all to see.
Installation of the internal floor screed has now commenced. This brings all internal floors up to their final level whilst at the same time encapsulating all of the under-floor heating which is installed to the entire floor area.
Keep your eye out for a mobile tower crane which will be visiting the site soon to lift some key items of plant to the roof - always an interesting sight.
Keep your eye out for a mobile tower crane which will be visiting the site soon to lift some key items of plant to the roof - always an interesting sight.
Morgan Sindall are hosting a charity event at the village hall on Friday 25 August which will include a barbecue to raise money for the The Lighthouse Charity. Please look at the post for Thursday 17 August for more information. See you there.